Blog home >

DETROIT, Michigan, December 30, 2008 (ENS) – In long-running case that affects the scope of federal jurisdiction over wetlands and other waters, developer John Rapanos and related defendants agreed Monday to resolve violations of the Clean Water Act at three sites in Midland and Bay counties, Michigan.

Rapanos has agreed to pay a $150,000 civil penalty and will spend an estimated $750,000 to mitigate for 54 acres of wetlands that were filled without authorization under the Clean Water Act, according to a joint statement by the Justice Department and U.S. Environmental Protection Agency.

While Rapanos did not admit doing anything wrong, he has agreed to preserve an additional 134 acres of wetlands that were unaffected by the unauthorized activity. Under the agreement, the preservation of these areas will be enforced through a conservation easement held by the state of Michigan.

“After litigating this case for a number of years, we are pleased to reach a settlement that so strongly benefits the environment and serves the public interest,” said Ronald Tenpas, assistant attorney general for the Justice Department’s Environment and Natural Resources Division.

“This longstanding case demonstrates that EPA continues to vigorously pursue violations of the Clean Water Act that adversely affect wetlands,” said EPA Regional Administrator Lynn Buhl.

“The settlement will benefit the environment in Bay County by preserving a substantial amount of wetlands that play a vital role in water quality, flood control and fisheries,” she said.

In the late 1980s, Rapanos filled 54 acres of wetland that he owned with sand in preparation for the construction of a mall and residences without filing for a permit from the U.S. Army Corps of Engineers. He dug an extensive network of ditches to dry out the sites, which resulted in excavated dirt being sidecast into wetlands.


A Michigan wetland, not the Rapanos property (Photo by
Dawn Ulmer)

Rapanos argued that the land was not a wetland and that he was not breaking the law, but his own consultant and state employees disagreed.

The original enforcement action was filed against Rapanos in 1994. Rapanos was convicted of two felonies for filling wetlands in violation of law in 1995. The conviction was overturned and restored several times but, in the end, he was forced to serve three years of probation and pay $5,000 in fines.

Eventually, Rapanos appealed the civil case against him, which included millions of dollars of fines, to the Supreme Court of the United States.

Rapanos challenged the EPA’s findings that the filled wetlands were under federal jurisdiction under the Clean Water Act.

The case turned on the legality of the federal regulations that define waters of the United States. The focus was on regulation of wetlands adjacent to non-navigable tributaries of traditional navigable waters and regulation of wetlands separated from such tributaries by a berm.

Rapanos’ land is 20 miles from the nearest navigable waterway, a Lake Huron tributary river. However, the term “navigable waterway” has been broadly interpreted by the U.S. Environmental Protection Agency to include areas connected to or linked to waters via tributaries or other similar means.

The 2006 Supreme Court litigation determined that Rapanos did fill wetlands under federal jurisdiction. But the Supreme Court sent the case back to the federal district court in Detroit, saying regulators might have exceeded their authority in preventing Rapanos and another landowner from developing their properties.

That ruling eventually led to Monday’s settlement.

But the Supreme Court’s 5-4 decision left the law on federal jurisdiction over waters of the United States and adjacent wetlands unclear.

The plurality opinion, authored by Justice Antonin Scalia, joined by Justices Clarence Thomas, Samuel Alito and Chief Justice John Roberts, interpreted “waters” under the Clean Water Act to be limited to “only those relatively permanent, standing or continuously flowing bodies of water ‘forming geographic features’ that are described in ordinary parlance as ’streams … oceans, rivers [and] lakes.’”

This definition does not include channels through which water flows intermittently, or channels that periodically provide drainage for rainfall.

Regarding “adjacent” wetlands, the plurality argued that “only those wetlands with a continuous surface connection to bodies that are ‘waters of the United States’ in their own right, so that there is no clear demarcation between ‘waters’ and wetlands ‘adjacent to’ such waters, are covered by the Clean Water Act.”

Chief Justice Roberts, in a concurring opinion, suggested that lower courts and regulated entities would have to “feel their way on a case-by-case basis.”

Justice John Stevens wrote a dissenting opinion in the case, joined by Justices David Souter, Ruth Bader Ginsburg and Stephen Breyer. The dissenting justices argued that the Supreme Court had previously upheld the regulation of wetlands adjacent to tributaries of navigable waters and that the court should defer to the agencies’ regulation of wetlands adjacent to non-navigable tributaries.

The Supreme Court’s deciding vote was cast by Justice Anthony Kennedy, who in a separate opinion steered a middle course between the opposing sides. Kennedy found that water draining from the Rapanos property does, in fact, flow into a stream and then into a navigable lake 20 miles away. But Kennedy said that just because water drains into a distant navigable lake is not in itself enough to trigger the wetlands protections under the Clean Water Act.

Exactly what would be sufficient remained unclear in his opinion.

Following the Supreme Court’s divided ruling in the Rapanos case, confusion has reigned among the agencies, the regulated community, and the courts over the definition of which waters are covered by the Clean Water Act.

Nevertheless, the consent decree to settle the Rapanos civil complaint was lodged Monday in the U.S. District Court in Detroit. It is subject to a 30-day comment period and final court approval. A copy of the proposed consent decree is available on the Justice Department website at www.usdoj.gov/enrd/Consent_Decrees.html.

There is a parallel criminal matter that is still pending and is not affected by the settlement under this agreement.

View This Story On Eco–mmunity Map.



NEW ORLEANS, Louisiana, December 29, 2008 (ENS) – Defense of Greater New Orleans’ most vulnerable area from storm surge has begun with the groundbreaking for the Inner Harbor Navigation Canal Lake Borgne Surge Barrier Project, the largest design-build civil works project in Corps history.

It is unusual for a civil works project to be designed and constructed simultaneously, but the Corps says the expedited process is necessary given the compressed timeframe to achieve 100-year flood protection in 2011.

When completed, the $700 million surge barrier, similar to a floodwall but much larger, will run for nearly two miles near the confluence of the Gulf Intracoastal Waterway and the Mississippi River Gulf Outlet. The 26 foot high barrier will run north-south from a point just east of Michoud Canal on the north bank of the waterway and just south of the existing Bayou Bienvenue flood control structure.

Navigation gates will be constructed where the barrier crosses the GIWW and Bayou Bienvenue to reduce the risk of storm surge coming from Lake Borgne and/or the Gulf of Mexico. The openings for each gate will be 150 feet wide.

Another navigation gate is planned for the Seabrook vicinity where the Inner Harbor Navigation Canal meets Lake Pontchartrain to block storm surge from entering the canal from the lake.


Confluence of the Mississippi River Gulf Outlet,
left, and the Gulf Intracoastal Waterway
(Photo courtesy USACE)

The surge barrier is a new feature, authorized by Congress in 2006, the year after hurricanes Katrina and Rita devastated the area. It is expected to reduce the risk of storm damage to some of the region’s most vulnerable areas – New Orleans East, metropolitan New Orleans, the 9th Ward, St. Bernard Parish and Gentilly – to a one percent chance in any given year.

“This is territory we must defend, and we must defend it with all of our ingenuity, and with all of our strength, and with all of our determination, and with every fiber of our being,” said John Paul Woodley, assistant secretary of the Army for public works, during the floating groundbreaking ceremony December 5. It was attended by more than 100 people aboard an Army Corps of Engineers enclosed barge towed to the construction site.

“To achieve these project goals, the Corps, the state, our local partners and the local communities must all work together. It’s all about teamwork,” said Karen-Durham-Aguilera, the Corps’ Task Force Hope director.

Advance measures will provide some protection for the area in 2009 although the barrier is not expected to be complete until 2011.

The advanced measures include a concrete barrier and a swinging navigation gate on the Gulf Intracoastal Waterway that would allow navigation to bypass the construction of the concrete floodwall and at the same time provide protection from surges.

Additionally, temporary retaining structures called coffer dams would be built at both the Gulf Intracoastal Waterway bypass swing gate and the location of the Bayou Bienvenue gate to provide risk reduction until the gates are complete.

A second level of risk reduction in the short term will be achieved by installing concrete caps on top of the concrete barrier, which will raise the level of the barrier to 20 feet.

For a separate project that is also aimed at reducing flood risk in the New Orleans area, the Corps is overseeing the $13.6 million Mississippi River Gulf Outlet closure structure.

The Mississippi River Gulf Outlet is a former federal navigation channel opened in 1968 to provide a short route between the Port of New Orleans and the Gulf of Mexico. On August 29, 2005, Hurricane Katrina made landfall in the area, causing widespread property and environmental damages. Since the storm, the shipping channel has not been maintained although navigation has continued.

On December 16, the Corps issued a Notice to Proceed to the construction contractor, Pine Bluff Sand and Gravel Company of Pine Bluff, Arkansas. The contractor will dump 430,000 tons of rock across 10 acres of water bottom.

Building the structure will end more than 45 years of navigation on the recently de-authorized federal navigation channel.

“The Corps of Engineers and the State of Louisiana are working faster than ever to provide protection to New Orleans and St. Bernard Parish by cooperating in the building of a surge barrier for the Inner Harbor Navigation Canal and closing the Mississippi River Gulf Outlet,” said Coastal Protection and Restoration Authority Chairman Garret Graves. “This shows what our partnership is capable of accomplishing and hopefully the kind of pace we will continue to take when building other restoration and protection projects.”

Since Hurricane Katrina flooded New Orleans when levees gave way, Corps leaders have pledged to provide the region with protection from a 100-year storm surge by the start of the 2011 hurricane season or “break our backs trying.” A banner draped across the Corps headquarters’ entrance in New Orleans announces the pledge.

To do that, the Corps and its consultants are designing hundreds of upgrades along the entire 350-mile levee system, including raising the height of the lakefront levee across Metairie and Kenner.

Future work in the area will include other coastal wetlands restoration projects. As organic material is dredged from waterways in preparation for new construction, it will be deposited in nearby wetlands habitat to enhance environmental conditions.

The Corps is working closely with federal and state partners to produce a supplement to the Mississippi River Gulf Outlet closure plan that will address ecosystem restoration in areas affected by the MRGO channel. Potential plan features may include marsh creation, shoreline protection, barrier island rebuilding, and freshwater diversions from the Mississippi River.

View This Story On Eco–mmunity Map.



HARRISBURG, Pennsylvania, September 3, 2008 (ENS) – Pennsylvanians will have a chance to provide input on how the commonwealth manages its water resources during a series of public meetings to be held across the state this month.

The Department of Environmental Protection, along with members of six regional water resources committees, will accept testimony on the draft state water plan that is being developed in accordance with the Water Resources Planning Act.

Developing the plan is the first step in analyzing problems and needs associated with specific water-related activities, such as stormwater management, flood control and navigation, state water officials say.

“This document will serve as a blueprint that guides sustainable water use throughout the commonwealth for the next 30 years,” said DEP Deputy Secretary for Water Management Cathy Curran Myers.


Pennsylvania’s Susquehanna River (Photo
courtesy Lancaster County)

By the end of 2008, the Water Resources Planning Act requires the DEP to develop a new state water plan that includes inventories of water availability, an assessment of current and future water demands, an evaluation of resource management alternatives, and proposed methods of implementing recommended actions.

“Our water resources are important to our economy and our quality of life, so it’s essential that we have a plan in place that ensures that we are good stewards of these precious assets,” Myers said. “Once finalized, this plan will serve as a tool for everyone – for the public, for municipalities, and for businesses interested in creating jobs here.”

Each public meeting will be preceded by an open house from 5 pm to 6 pm to give people a chance to review displays and maps of the respective regions. From 6 pm to 7:30 pm, DEP staff and members of the respective regional committees will give presentations on the draft plan and conduct an informal discussion period. The department will begin accepting formal comments on the draft plan beginning at 7:30 pm

Anyone planning to testify should register in advance by contacting Karen Price at 717-783-9499 or by e-mailing kprice@state.pa.us.

A written copy of the testimony should be provided to department staff at the hearings. Written testimony also will be accepted through September 30 and may be sent to Leslie Sarvis, DEP Water Planning Office, P.O. Box 2063, Harrisburg, PA 17105-2063.

Each regional water resources committee will conduct a regular business meeting from 2:30 pm to 4 pm on the same date and location as the public meeting. The business meetings are open to the public.

The draft state water plan and agendas for each meeting are available through the Public Participation link at www.depweb.state.pa.us, keyword: Participate.

Public meeting dates and locations:

* Sept. 8 – Ohio Regional Water Resources Committee meeting, Seven Fields Community Center, 380 Castle Creek Dr., Seven Fields, Butler County. For information, contact Lori Mohr, DEP Water Planning Office, 717-787-4628 or laumohr@state.pa.us.

* Sept 9 – Great Lakes Regional Water Resources Committee meeting, Erie County Conservation district, 1927 Wager Rd., Erie. For information, contact Lori Mohr, DEP Water Planning Office, 717-787-4628 or laumohr@state.pa.us.

* Sept. 11 – Delaware Regional Water Resources Committee meeting, Room 605 Fowler Family Southside Centre, Northampton Community College, 511 E. Third St., Bethlehem. For information, contact Leslie Sarvis, DEP Water Planning Office, 717-772-5634 or lsarvis@state.pa.us.

* Sept. 15 – Lower Susquehanna Regional Water Resources Committee meeting, Radisson Penn Harris Hotel & Convention Center, 1150 Camp Hill Bypass, Camp Hill, Cumberland County. For information, contact Leslie Sarvis, DEP Water Planning Office, 717-772-5634 or lsarvis@state.pa.us.

* Sept. 17 – Upper/Middle Susquehanna Region Water Resources meeting, Holiday Inn, 100 Pine St., Williamsport. For information, contact Lori Mohr, DEP Water Planning Office, 717-787-4628 or laumohr@state.pa.us.

* Sept. 18 – Potomac Regional Water Resources Committee meeting, Multi-Purpose Center, Penn State Mont Alto Campus, One Campus Dr., Mont Alto, Franklin County. For information, contact Leslie Sarvis, DEP Water Planning Office, 717-772-5634 or lsarvis@state.pa.us.

View This Story On Eco–mmunity Map.



Advertisement